Most commercial premises should have an Electrical Installation Condition Report (EICR) at least every five years, and some higher-risk premises every one to three years, based on the maximum intervals recommended in the IET’s guidance to BS 7671. There is no single fixed legal interval for most businesses, but the Electricity at Work Regulations 1989 require electrical systems to be maintained to prevent danger, and a regular EICR is the accepted way to show you have done that.
In short
- The law requires electrical systems at work to be maintained to prevent danger. It does not set one interval for every business.
- IET guidance recommends maximum intervals: typically five years for offices, shops and hotels, three years for industrial premises, and one year for places like swimming pools and petrol stations.
- The inspector sets the next due date on the report and can make it shorter if the condition or use of the installation calls for it.
- A report is unsatisfactory if it records any C1, C2 or FI observation.
- Flats and rented homes above or within commercial buildings fall under the separate five-year rule for rented homes.
What the law says
The Electricity at Work Regulations 1989
The key rule for workplaces is regulation 4(2) of the Electricity at Work Regulations 1989: “As may be necessary to prevent danger, all systems shall be maintained so as to prevent, so far as is reasonably practicable, such danger.” The regulations do not say how often to test. The Health and Safety Executive’s guidance says installations should be tested often enough that there is little chance of deterioration leading to danger, by someone competent to do it.
In practice, a periodic inspection and test, recorded on an EICR, is how a business shows it is meeting that duty. If there is an accident or a fire, the first thing an investigator or insurer is likely to ask for is evidence of maintenance, and a current EICR is the obvious document. Our EICR service covers commercial premises as well as homes.
Other rules that point the same way
- Fire safety. Under the Regulatory Reform (Fire Safety) Order 2005, the responsible person for non-domestic premises must carry out a fire risk assessment. Faulty electrics are a common fire risk, so fire risk assessors often ask to see the EICR.
- Insurance. Many commercial insurers set their own inspection requirements in the policy. Check yours, because the insurer’s interval can be stricter than the guidance.
- Leases. Commercial leases often say who is responsible for the fixed wiring and how often it must be inspected. Read the repair and compliance clauses.
- Rented homes in the building. If there are flats above a shop or within a mixed-use building, the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020 require the landlord to have those homes inspected at least every five years and to give tenants a copy of the report.
Recommended intervals by type of premises
BS 7671, the IET Wiring Regulations, requires periodic inspection and testing, and the IET’s Guidance Note 3 on inspection and testing gives recommended maximum intervals between inspections. The table shows common examples. These are maximums: the inspector will set the actual date on your report.
| Type of premises | Recommended maximum interval |
|---|---|
| Offices, shops and general commercial premises | 5 years |
| Hotels | 5 years |
| Schools and other educational premises | 5 years |
| Industrial premises and factories | 3 years |
| Leisure complexes and theatres | 3 years |
| Swimming pools, petrol stations and caravan parks | 1 year |
| Construction site installations | 3 months |
Some premises may need a shorter interval than the table suggests, for example where the installation is old, heavily used, exposed to damp, dust or vibration, or has a history of faults. Premises should also be inspected on a change of occupier or change of use, after alterations, or after damage such as a flood or fire.
Commercial and domestic EICRs: what is different
The purpose is the same, but a commercial EICR usually involves more.
- Bigger and more complex installations. Three-phase supplies, several distribution boards, sub-mains and a larger number of circuits.
- Sampling. On larger sites, the inspector and client agree the extent of the inspection and any limitations beforehand, and some items may be sampled rather than every one being tested. Any limitations must be written on the report.
- Isolation. Some tests need circuits switched off. That usually needs planning around trading hours, IT systems and refrigeration, and may mean working early or late.
- Separate systems. An EICR covers the fixed electrical installation. Emergency lighting, fire alarms and portable appliances each have their own inspection and testing, and are not included unless agreed.
What the codes on an EICR mean
Every defect or observation on an EICR is given a code, and the codes decide whether the report is satisfactory.
| Code | Meaning | What happens next |
|---|---|---|
| C1 | Danger present, risk of injury | Immediate action. The inspector will make it safe, usually by isolating the circuit, before leaving |
| C2 | Potentially dangerous | Urgent remedial work needed |
| C3 | Improvement recommended | Not dangerous, but worth doing. Does not by itself make the report unsatisfactory |
| FI | Further investigation required without delay | Something could not be fully assessed and needs looking into |
If the report contains any C1, C2 or FI, the overall result is unsatisfactory. The remedial work should be done by a competent electrician, who then provides written confirmation (and a certificate for the work where appropriate). Our electrical repairs and fault finding team handles remedial work after an inspection.
How to prepare for a commercial EICR
- Find the last report and any certificates for work done since. The inspector will want to see them.
- Locate every distribution board and make sure the inspector can reach them.
- Agree the extent and timing, including any areas that cannot be switched off during trading.
- Warn staff and tenants about planned power interruptions.
- Back up IT systems and plan for refrigeration, alarms and anything that must stay on.
- Make sure circuit charts are available, or ask for them to be updated as part of the inspection.
Who is responsible?
The duty sits with whoever has control of the electrical installation. In a building you own and occupy, that is you as the employer. In a leased building, it depends on the lease: often the landlord is responsible for the landlord’s supply and common parts, and the tenant for the installation inside their unit, but leases vary. If in doubt, ask your solicitor or managing agent before the inspection, not after. For rented homes, our landlords page covers the domestic rules.
What it costs with Vantage
We give you the price for a commercial EICR before we start, based on the size of the installation, the number of boards and circuits, and when the work has to be done. Any remedial work is quoted separately before we do it, so you can decide how to proceed. Every rate is published on our prices page. Our remedial work comes with a 12 month labour guarantee.
Frequently asked questions
Is an EICR a legal requirement for commercial property?
There is no law that names an EICR for most commercial premises, but the Electricity at Work Regulations 1989 require systems to be maintained to prevent danger. A periodic EICR is the recognised way to show you are meeting that duty, and insurers, landlords and fire risk assessors often ask for one.
How long is a commercial EICR valid for?
The report states the date of the next inspection, set by the inspector. For offices and shops the recommended maximum is usually five years, but it can be shorter depending on the condition, age and use of the installation.
What is the difference between an EICR and PAT testing?
An EICR covers the fixed wiring: the distribution boards, circuits, sockets, switches and fixed equipment. PAT testing covers portable and plug-in appliances. A business normally needs both, on their own schedules.
Can my business stay open during an EICR?
Usually, yes. Most of the visual inspection can be done during normal hours. Tests that need circuits switched off can be planned for quiet periods or outside trading hours.
What happens if my commercial EICR is unsatisfactory?
The inspector will make any immediate danger safe and list the C2 and FI items that need attention. You should arrange remedial work promptly, keep the confirmation that it has been done, and keep both documents with the report.
Commercial electrical testing in Hertfordshire, Bedfordshire and Cambridgeshire
If your business premises are due an inspection, or you are not sure when the last one was done, our electricians can carry out the EICR and any remedial work. See our electrical safety certificate page and our commercial services, or call 01462 506374.
What our customers say
Speak to a local engineer
Vantage Plumbing and Heating covers Hertfordshire, Bedfordshire and the surrounding areas. Call and talk to an engineer, or send us the details and we will come back to you with a price.
Gas Safe registered, number 956889. Emergency line answered 24/7.