Commercial EV Charger Installation: A Guide for Businesses
Hertfordshire, Bedfordshire & Cambridgeshire
Commercial EV charger installation starts with a site survey to check how much spare electrical capacity you have, then choosing the right number and type of chargers, notifying or applying to the local network operator, and installing and commissioning the chargers to BS 7671 and the IET’s code of practice for EV charging. For most workplaces, 7kW or 22kW AC chargers with load management are the practical choice; rapid DC chargers suit sites where vehicles need to charge quickly, but they need a much larger power supply.
In short
- The size of your electrical supply usually decides how many chargers you can have and how fast they can be.
- Most workplace chargers are 7kW single-phase or 22kW three-phase AC. Rapid chargers are DC and need a far bigger supply.
- Load management lets several chargers share the available power without tripping the supply.
- Private workplace chargers must meet the Smart Charge Points Regulations. Public chargers have their own rules.
- Plan the groundworks, cable routes, bay layout, software and who pays for charging before the first cable goes in.
Who is charging, and for how long?
The right setup depends on who will use the chargers and how long their vehicles are parked. Getting this right at the start saves money and disappointment later.
| Use | Typical parking time | Charger type that usually suits |
|---|---|---|
| Staff at a workplace | Most of the working day | 7kW AC, or 22kW AC where the supply allows |
| Company fleet or vans returning to base | Overnight | 7kW to 22kW AC, with load management across the fleet |
| Customers or visitors | An hour or two | 22kW AC, or rapid DC if the stop is short |
| Fleet vehicles needing a quick top-up | Minutes | Rapid DC (50kW and above) |
| Public charging | Varies | Depends on the site. Public chargers must meet extra regulations |
A car parked for eight hours does not need a fast charger. Many electric cars can only accept 7kW or 11kW from an AC charger anyway, so a 22kW charger will not always charge them any faster. Matching the charger to the dwell time means you can fit more chargers on the same supply.
Our EV charging page covers the chargers we install for homes and businesses.
Charger types explained
AC chargers (7kW and 22kW)
AC chargers are the standard choice for workplaces. A 7kW charger runs on a single-phase supply. A 22kW charger needs a three-phase supply, which most commercial buildings have. The car’s own onboard charger converts the power to charge the battery, which is why the car, not just the charger, limits the charging speed.
Rapid DC chargers (50kW and above)
Rapid chargers convert the power to DC inside the charger and feed it straight to the battery, so they are much faster. They are also much larger, cost far more to buy and install, and usually need a significant supply upgrade. They make sense for fleets that need quick turnarounds or for sites offering public charging.
How a commercial installation works
- Site survey. The electrician looks at your incoming supply, main switchgear and distribution boards, the route from the board to the parking area, the ground surface, and where the chargers will physically go.
- Load assessment. They work out your maximum demand, how much capacity is spare and how many chargers the supply can support, with and without load management.
- Network operator. Charge points have to be notified to your local distribution network operator (DNO). Larger installations, or ones that need more capacity, need an application and approval before installation, which can take time. Allow for this in your plans.
- Design. The design covers cable sizes, protective devices, earthing, the number and position of chargers, load management and any groundworks.
- Groundworks and containment. Trenching and ducting across a car park, cable routes on walls, and bollards or wheel stops to protect the chargers from vehicles.
- Installation. Chargers are mounted on walls or on pedestals and wired back to a suitable distribution board, often with a new sub-main as part of wider electrical installation work.
- Testing and commissioning. The installation is tested and certified to BS 7671, the chargers are connected to their software, and the network operator is notified if that was not done beforehand.
- Handover. You get the certificates, instructions for the software and details of any maintenance the manufacturer recommends.
Why earthing and protection matter EV chargers sit outdoors, next to vehicles and wet ground, and deliver a lot of power for hours at a time. The wiring regulations (BS 7671) have a specific section on EV charging, including restrictions on how a PME earth from the supply can be used for outdoor charge points. Many chargers include built-in protection for this, but the earthing arrangement still has to be designed properly. Charger installation is a job for a qualified electrician, and our guide on how to choose an electrician covers what to check.
Load management
Load management (sometimes called load balancing) lets several chargers share the power available. Dynamic load management monitors the building’s demand and gives the chargers whatever is left, slowing them down when the building is busy and speeding them up when it is quiet. It often means you can install more chargers without upgrading your supply, which can save a great deal of time and cost.
Software, access and billing
Most commercial chargers connect to a back-office platform. This lets you:
- control who can charge (staff only, fleet only, visitors with a card or app)
- charge users for the electricity if you want to, or offer it free
- see how much each charger is used
- monitor faults and uptime
Chargers that use an open communication standard (OCPP is the most common) give you more choice of software provider in future. Ask about this before you buy.
The rules that apply
- BS 7671 and the IET Code of Practice. Every charger installation must meet the wiring regulations, and the IET’s Code of Practice for EV charging equipment installation sets out good practice.
- Smart Charge Points Regulations 2021. Private charge points sold for use at home or at a workplace in Great Britain must have smart functionality and meet security requirements. Rapid charge points and public charge points are outside these regulations.
- Public Charge Point Regulations 2023. If your chargers are open to the public, they must meet further requirements covering areas such as contactless payment, pricing shown in pence per kWh, open data and a free 24/7 helpline.
- Building Regulations Part S. New non-residential buildings, and some major renovations, with more than 10 parking spaces need at least one charge point and cable routes for one in five spaces.
- Planning and landlord consent. Many charge points in off-street car parks do not need planning permission, but there are limits, and listed buildings or conservation areas may need consent. If you lease your premises, check you have the landlord’s permission.
Government grants for workplace charge points are also available to eligible businesses, charities and public sector organisations until 31 March 2027, subject to the scheme’s own rules and installer requirements. Check the current rules on gov.uk before you apply.
Mistakes to avoid
- Choosing chargers before checking the supply. The supply decides what is possible.
- Fitting fewer, faster chargers when more, slower ones would suit. Staff parked all day rarely need 22kW.
- Forgetting future growth. Running extra ducting while the ground is open costs very little compared with digging again later.
- Ignoring the software. Access control and billing are often what make or break a workplace charging scheme.
- Skipping maintenance. Chargers are outdoor electrical equipment. Include them in your inspection and testing schedule, alongside your commercial EICR.
How we price it
Installations are quoted as a fixed price after a free survey, so the price you agree is the price you pay. The survey is where we check your supply, the cable routes and the groundworks, so the quote reflects your site rather than a guess. You can see how we charge for other electrical work on our prices page. Our work comes with a 12 month labour guarantee.
Frequently asked questions
How long does a commercial EV charger installation take?
A small workplace installation on an existing supply can be straightforward once the survey and design are done. Larger sites, groundworks and anything that needs network operator approval or a supply upgrade take longer, so allow time for the approval process in your plans.
Do I need three-phase power for commercial EV chargers?
For 22kW AC chargers, yes. 7kW chargers run on single-phase. Most commercial buildings already have a three-phase supply, but its spare capacity is the real limit.
How many EV chargers can my business install?
It depends on the spare capacity of your supply and whether you use load management. A load assessment during the survey tells you how many chargers your supply can support and whether an upgrade would be needed for more.
Do workplace EV chargers need to be smart?
Yes. Private charge points sold for use at a workplace in Great Britain must meet the Smart Charge Points Regulations 2021, which require smart functionality and security features. Rapid and public charge points are covered by different rules.
Can I charge staff or visitors to use the chargers?
Yes. Most commercial chargers connect to software that controls who can charge and what they pay, or you can offer charging free. Chargers open to the public must follow the Public Charge Point Regulations 2023.
EV charging for businesses in Hertfordshire, Bedfordshire and Cambridgeshire
If you are planning charge points for staff, fleet or customers, our electricians can survey your site, check your supply and install the chargers. See our commercial services and EV charging pages, or call 01462 506374.
What our customers say
Speak to a local engineer
Vantage Plumbing and Heating covers Hertfordshire, Bedfordshire and the surrounding areas. Call and talk to an engineer, or send us the details and we will come back to you with a price.
Gas Safe registered, number 956889. Emergency line answered 24/7.