How Long Does a Bathroom Renovation Take? Stage by Stage
Hertfordshire, Bedfordshire & Cambridgeshire
A full bathroom renovation in the same layout usually takes one to two weeks of work on site, and a larger job that moves the toilet, creates a wet room or changes the room itself can take two to three weeks or more. Add the time for the survey, design and ordering products before work starts, and the whole project from first visit to first shower is often a matter of weeks to a couple of months, mostly depending on product lead times.
- A straightforward refit in the same layout: roughly one to two weeks on site.
- Moving the toilet, bath or shower, or building a wet room: two to three weeks or more.
- Before work starts, allow time for the survey, design choices and delivery of the suite and tiles.
- Drying and curing times for plaster, screeds, waterproofing and adhesives set the pace, not just labour.
- Hidden problems such as rotten floorboards or old pipework are the most common cause of delays.

Bathroom renovation timescales by type of job
| Type of job | Typical time on site | Why |
|---|---|---|
| Suite swap in the same position, minimal tiling | A few days | Pipework, waste and electrics stay where they are |
| Full refit in the same layout, fully tiled | About one to two weeks | Strip out, first fix, boarding, tiling, second fix and finishing |
| Refit with a layout change | Two to three weeks | Waste and supply pipes rerouted, the toilet may need a new route to the soil pipe |
| Wet room | Two to three weeks or more | Floor falls, a waterproofing system and more drying time |
| En suite in a new space | Varies widely | Depends on building work, drainage routes and any Building Regulations sign-off |
These are typical ranges for an ordinary home. The survey is where your installer should work out what your particular job needs and give you a realistic plan. Our bathroom renovation team plans every job this way before a date is booked.
The stages of a bathroom renovation
Before work starts
- Survey and measure. The installer checks the room, the floor, the walls, the water pressure, the waste routes and where the soil pipe runs.
- Design and choose products. You pick the suite, tiles, brassware, lighting and storage. Changing your mind later is one of the biggest causes of delays, so decide early.
- Order and deliver. Some items are in stock. Others, particularly made-to-measure shower screens, furniture and some tiles, can take several weeks.
On site
- Strip out. The old suite, tiles and sometimes plaster or boards are removed and taken away. This is often a single day, but it is also when hidden problems appear.
- Repairs to the structure. Rotten floorboards, damaged joists or loose plaster are put right before anything new goes in.
- First fix plumbing and electrics. New supply and waste pipes are run and the cabling for lights, extractor fan, shaver point or electric towel rail goes in while the walls and floor are open.
- Boarding and plastering. Walls and floors are prepared with suitable boards or plaster. Plaster and any new floor screed must dry before tiling.
- Waterproofing. Showers and wet rooms are tanked with a waterproofing system. BAL, for example, says its Waterproof 1C membrane needs at least 2 hours to dry before tiling, and floors usually need two coats.
- Tiling. Walls and floor are tiled. This is often the longest single stage, and the size and pattern of the tiles make a big difference.
- Grouting. How soon grouting can start depends on the adhesive. A rapid-setting adhesive such as BAL Turbo Set can be grouted after 30 minutes, while standard-setting adhesives need longer.
- Second fix. The toilet, basin, bath or shower tray, taps, screen, furniture, lights and fan are fitted and connected.
- Sealing and finishing. Silicone sealant goes round the bath, tray and basin. Leave it to cure for the time the sealant maker states before you use the bath or shower.
- Testing and handover. Everything is tested for leaks and correct operation, and you are shown how it all works.
What makes a bathroom renovation take longer
- Hidden damage. Old leaks often leave rotten boards or joists under the bath or toilet. These must be repaired properly before the new floor goes down.
- Moving the toilet. The toilet needs a route to the soil pipe with enough fall. If the new position makes this difficult, extra work or a different solution is needed.
- New screeds. A new floor screed has to dry before it can be tiled. BAL advises that anhydrite (gypsum-based) screeds can take a lot longer to dry than sand and cement, and moisture should be tested before tiling.
- Large-format or patterned tiles. Big tiles need very flat surfaces and careful handling. Herringbone and other patterns take longer to set out and cut.
- Product delays. A missing tap or a late shower screen can hold up the final stage even when everything else is done.
- Changes mid-job. Moving a basin or switching tiles once work has started means rework.
- Electrical sign-off. Under Approved Document P, installing a new circuit or adding to or altering circuits in a room containing a bath or shower is notifiable work, so it must be done and certified by a competent electrician.
- Ventilation. Approved Document F sets a minimum intermittent extract rate of 15 litres per second for a bathroom, and when a bathroom is refurbished any existing fan should be kept or replaced. Upgrading a weak fan can add a little time but is worth it.
Living with a bathroom renovation
If this is your only bathroom, plan ahead for the days when you have no toilet or shower.
- Ask your installer which days the toilet will be out of action. On many jobs it can be reconnected temporarily at the end of the day.
- Arrange to use a gym, a relative’s home or a neighbour for showers during the middle of the job.
- Expect the water to be off for short periods while pipework is connected.
- Keep a clear route from the front door to the bathroom for the strip out and deliveries.
- Clear the bathroom and airing cupboard before day one, and move anything fragile from the landing.
How to keep your renovation on schedule
- Make every design decision before the start date, including tiles, grout colour and where the towel rail goes.
- Have all the products on site, checked and undamaged, before work starts.
- Agree who is supplying what in writing. Our guide to what a bathroom installation quote should include covers the details to look for.
- Ask what happens if hidden damage is found, and how it will be priced.
- Choose an installer who handles the plumbing, tiling and electrics as one coordinated job. Our guide on how to choose a bathroom installer explains what to check.
Plan the water and electrics properly Bathrooms combine water and electricity in a small space. Electrical work near a bath or shower must follow the Building Regulations and the wiring regulations, and a new circuit must be installed by a competent person and certified. Do not use a newly sealed bath or shower until the sealant has cured, and report any drip or damp patch straight away.
How we price it
Installations are quoted as a fixed price after a free survey, so the price you agree is the price you pay. The survey is also where we set out how long your job will take and the order of work. For an idea of what affects the overall price, see our bathroom renovation cost guide, and our other rates are published on our prices page. Every bathroom we fit comes with a 2 year guarantee.
Frequently asked questions
Can a new bathroom be fitted in a day?
Only a very simple suite swap with little or no tiling might be done in a day or two. A full renovation with new tiles and pipework takes much longer, because boards, waterproofing and adhesives all need time to dry and cure.
How long does it take to rip out and refit a bathroom?
The strip out itself is often a day. The complete rip out and refit of a standard bathroom in the same layout usually takes one to two weeks, and longer if the layout changes or repairs are needed.
What is the hardest part of a bathroom renovation?
Usually the preparation nobody sees: getting floors and walls flat, sound and properly waterproofed. Good tiling and a watertight shower depend on it, and it is where rushing causes problems later.
How long does a small bathroom renovation take?
A small bathroom or cloakroom is not always much quicker, because the same stages and drying times apply. Less tiling helps, but a small room with a layout change can take as long as a larger simple refit.
How long after tiling can I use the shower?
That depends on the adhesive, grout and sealant used. Each has a curing time set by its manufacturer, so ask your installer when the shower can be used, and do not use it before then.
Bathroom renovations in Hertfordshire, Bedfordshire and Cambridgeshire
We handle the plumbing, tiling and finishing of your bathroom as one planned job, with a clear timetable agreed before we start. See our bathroom renovation page or call 01462 506374.
What our customers say
Speak to a local engineer
Vantage Plumbing and Heating covers Hertfordshire, Bedfordshire and the surrounding areas. Call and talk to an engineer, or send us the details and we will come back to you with a price.
Gas Safe registered, number 956889. Emergency line answered 24/7.
Bathroom fitters near you
Planning a new bathroom? Our own team designs and fits it
We cover Hertfordshire, Bedfordshire and Cambridgeshire. Choose your town:
Not listed? See all the areas we cover or call 01462 506 374