How Long Does Air Conditioning Installation Take?
Hertfordshire, Bedfordshire & Cambridgeshire
A single wall-mounted split air conditioner, with one indoor unit and one outdoor unit, is usually installed in a day. A multi-split system serving several rooms typically takes one to three days, and ducted or concealed systems that need ceiling or loft work take longer again.
- One indoor unit and one outdoor unit: usually a single day.
- Multi-split systems for two to five rooms: around one to three days.
- Ducted systems and jobs with long pipe runs, difficult access or new electrical circuits take longer.
- Much of the day is testing: pressure testing, pulling a vacuum and commissioning, which should never be rushed.
- The work must be done by an F-gas qualified engineer working for a certified company.

Air conditioning installation times by type of system
| Type of system | Typical time on site | What drives the time |
|---|---|---|
| Single split, one wall-mounted indoor unit | Usually one day | A short pipe run through an outside wall is the quickest job |
| Single split with a long or complicated pipe run | One to two days | Trunking, extra drilling, more refrigerant pipe and sometimes extra refrigerant |
| Multi-split, two to five indoor units on one outdoor unit | Around one to three days | Each indoor unit needs its own pipe, cable and drain route |
| Ducted or ceiling cassette system | Several days | Ceiling voids, loft space, ductwork and grilles |
| Replacing an existing system | Similar to a new install, sometimes longer | Refrigerant in the old system must be recovered before it is removed |
These are typical figures. Your installer should confirm the timescale for your home after a survey. When we plan an air conditioning installation, the survey is where we agree the unit positions and the pipe route, because those decide how long the job takes.
What happens on installation day
A typical single split installation follows these steps.
- Confirm positions. The engineer confirms where the indoor and outdoor units go, the pipe route, the drain route and where the power comes from.
- Fit the indoor unit bracket. The mounting plate is fixed level to the wall.
- Drill the wall. A hole is cut through the outside wall for the pipes, cable and condensate drain. Fujitsu’s instructions for one of its wall units, for example, call for a 65 mm hole that falls slightly towards the outside so water drains away.
- Run the pipes, cable and drain. Insulated copper refrigerant pipes, the interconnecting cable and the condensate drain are run to the outdoor unit, often in neat trunking on the outside wall.
- Mount the outdoor unit. It goes on wall brackets or a ground stand with anti-vibration mounts and the clearances the manufacturer specifies.
- Connect the power. The system is connected to a suitable electrical supply. Manufacturers usually specify a dedicated supply with its own protection.
- Pressure test. The refrigerant pipework is pressurised with dry nitrogen to prove there are no leaks.
- Pull a vacuum. A vacuum pump removes air and moisture from the pipes. The engineer checks that the vacuum holds before going further.
- Release the refrigerant. The valves on the outdoor unit are opened. Extra refrigerant is added if the pipe run is longer than the unit’s pre-charged length.
- Commission and hand over. The system is run in cooling and heating, temperatures and drainage are checked, and you are shown how to use the controls and app.
The pressure test and vacuum take time, and they are the steps most likely to be cut short by a rushed installer. They are what stop leaks and keep the system reliable, so they are worth waiting for.
What makes installation take longer
- Long pipe runs. Each outdoor unit is pre-charged with refrigerant for a set pipe length given in the manual. Longer runs need extra refrigerant and more time.
- Difficult walls. Thick stone walls, cavity walls with insulation and reinforced concrete all take longer to drill through cleanly.
- Working at height. An outdoor unit on an upper wall, or pipe runs across a first-floor wall, may need a tower or other access equipment.
- Condensate drainage. Where water cannot drain away by gravity, a condensate pump is fitted, which adds time.
- Electrical work. A new circuit is notifiable work under Part P of the Building Regulations. If the consumer unit needs upgrading, that adds more.
- Multiple rooms. Each extra indoor unit adds its own drilling, pipes, cable and drain.
- Internal pipe routes. Taking pipes through cupboards, floors or lofts to reach an inside room takes longer than a straight run out through an outside wall.
F-gas rules: who can install air conditioning
Split air conditioning systems contain fluorinated refrigerant gas. Government guidance says it is against the law to work with F gas without the correct qualifications. Engineers who install and service stationary air conditioning need an F-gas certificate in the right category, and the companies they work for need company certification. When a non-hermetically sealed split system is sold to an end user, the seller must also ask for the details of the qualified technician who will install it.
This is why a split system is not a DIY job, and why installation time is partly set by the testing the regulations and manufacturers expect. Vantage is Refcom F-Gas registered, REF1024550. Our guide on how to choose an air conditioning installer covers what to ask before you book.
Why this is not a DIY job Handling refrigerant without F-gas qualifications is against the law, and a system that is not pressure tested and evacuated properly can leak, lose performance and fail early. The electrical supply must be installed and certified by a competent person. Do not try to connect, vent or top up refrigerant yourself.
How to prepare for installation day
- Clear the wall where the indoor unit goes and about a metre in front of it.
- Move furniture and cover anything that could catch dust when the wall is drilled.
- Clear the outside area where the outdoor unit and pipe run will go.
- Make sure the engineer can reach your consumer unit.
- Keep a parking space free near the house if you can.
- Download the manufacturer’s app if you want Wi-Fi control, so it can be set up at handover.
After installation
At handover you should receive the paperwork for the system and the manufacturer’s guarantee details. Most manufacturers ask for the system to be serviced regularly to keep the guarantee valid, so it is worth booking air conditioning servicing at the recommended interval. Keep the filters in the indoor unit clean between services.
How we price it
Installations are quoted as a fixed price after a free survey, so the price you agree is the price you pay. You can start with our air conditioning quote, and our other rates are published on our prices page. Air conditioning brands we offer include Alpha, Panasonic and Fujitsu. Our installation work carries a 12 month labour guarantee.
Frequently asked questions
Can air conditioning be installed in one day?
A single wall-mounted split system usually can, if the pipe run is straightforward and the electrics are ready. Multi-room and ducted systems take longer.
How much mess does air conditioning installation make?
Drilling the wall makes some dust, which a good installer controls with dust sheets and extraction. After that the work is mostly fitting and testing, and the engineer should clean up before leaving.
Do I need to be home while air conditioning is installed?
Someone should be there at the start to confirm unit positions and at the end for the handover, so you know how to use the system. Many people stay in for the day.
How big is the hole for an air conditioning unit?
For a typical wall-mounted indoor unit, the hole through the wall is usually around 65 mm across, but the manufacturer’s instructions set the exact size. The hole is sealed around the pipes once they are fitted.
How long after installation can I use the air conditioning?
You can use it straight away. The engineer runs and checks the system at commissioning and shows you how to use it before leaving.
Air conditioning installation in Hertfordshire, Bedfordshire and Cambridgeshire
We survey every home before quoting, so you know exactly how long the installation will take and where everything will go. See our air conditioning installation page or call 01462 506374.
What our customers say
Speak to a local engineer
Vantage Plumbing and Heating covers Hertfordshire, Bedfordshire and the surrounding areas. Call and talk to an engineer, or send us the details and we will come back to you with a price.
Gas Safe registered, number 956889. Emergency line answered 24/7.
Air conditioning near you
Want air con fitted? We install and service it across the area
We cover Hertfordshire, Bedfordshire and Cambridgeshire. Choose your town:
Not listed? See all the areas we cover or call 01462 506 374